In Zachry, the Port of Houston Authority withheld critical concerns from Zachry during negotiation of the change order. What concern was withheld?
1) that the freeze wall method would destabilize existing piers
2) that the freeze wall method was developed by an Aggie and could not reliable
3) that the freeze wall method would take away environmental credits
4) that Zachry was not qualified to do the work