All of the following are reasons to stop crashing EXCEPT:
Options:
A. the project has been crashed to the desired duration.
B. the cost of additional crashing exceeds the benefit.
C. more than one path has become critical.
D. there are no critical activities that can be crashed further.

Respuesta :

The statement that does not refer to the reason that aids in project crashing is

(D) there are no critical activities that can be crashed further.

Explanation:

Project crashing basically refers to the method by which the duration of the project is reduced  .This can be done by

  • Reducing the time taken by one or more critical activity
  • By devoting more resources in order to complete the project as early as possible.
  • The cost associated with the project is also increased

In Crashing, the time is inversely related to the cost of the project.It means that if the time of the project increase then the project cost is reduced and if the time o/duration of the project decrease then the cost involved in the project increases