Answer:
0.408 hour / device
Step-by-step explanation:
As we know The army contract was for 4,707 devices that were produced by 16 workers which means 1 worker can produce: [tex]\frac{4707}{16}[/tex] ≈294 devices in 3 weeks.
<=> 294 devices= 3*40 hours
<=> 294 devices = 120 hours
<=> 1 device = 120/294 = 20/49 ≈ 0.408 hour
So it takes 0.408 hour for a worker to finish producing 1 devicein the army contract